Its been a long time coming but we are finally close. Our new 27,000 square foot state of the art training facility. The new facility will have 48' ceilings, 40 yd x 60 yd turf field, 4 bating, 2 at 50' and 2 at 60' for both softball and baseball. There will be a 3,000 square foot top notch gym, a conference / party room and a physical therapy office.
Stay tuned here for weekly updates.
9/25/24: The sewage module is approved by the health department. This means once the DEP approves, we can finally start digging.
10/14/24: Digging day. Today we finally started digging.
10/23/2024: Pouring concrete and continuing to form for the walls. Hoping to start putting in plumbing runs next week.
11/7/2024: Frost walls getting poured today and Duquesne Light onsite prepping for pole installation next week.
11/15/2024: Today a lot was getting done. New electric poles installed, plumbing rough ins inspected, frost walls done, and the floors are being prepped for concrete which will be poured on Monday and Tuesday. Building will hopefully be started first of December.
11/19/2024: So, a few big days for us. We poured roughly 460 yards of concrete. This will just about get the whole floor done. It will set for a while and soon the building can start being erected.